CIS provided personnel and an S-90 hammer to assist in a drive-drill-drive project that consisted of installing thirty 1056mm OD piles for the extension of an existing fuel terminal in Panama. While six of the piles installed were vertical, the other twenty four were diagonal piles with inclinations as steep as one on four. The operation was conducted from a jack-up barge with a mobile crane on board.